Written for general builders, groundworkers, carpenters and joiners, roofers, plasterers, bricklayers and kitchen and bathroom fitters in the UK, from one-van firms to small main contractors.
The short version
- Work out the payment dates when you apply.Due date, pay less deadline and final date, from the contract or the Scheme. Once money is late, the pay less deadline has passed.
- Demand the full notified sum in writing.No valid pay less notice by the deadline means no deduction. Cite section 111 and claim interest.
- Suspend on notice, or adjudicate.If still unpaid after the final date, give written notice of intention to suspend first. Adjudication is open at any time.
Say you apply for £48,000, receive no payment notice, and get paid £35,500, with a note about a contra charge. Or nothing arrives because the main contractor says it has not been paid itself. On a business-to-business construction contract you have more than a chasing letter, but every step runs on dates, so work them out first.
The payment notice timetable
The payer gives a payment notice within 5 days of the due date, saying the sum it considers due and how it is calculated: that is the notified sum. If no payment notice is given, an application you made as the contract allows before that deadline, stating the sum and its basis, counts as your notice and sets the notified sum; otherwise you can serve your own notice of the sum due and its basis, and the final date moves back by as many days as your notice came after the payer's deadline. To pay less than the notified sum the payer must serve a pay less notice, with the sum and the basis, by the contract's deadline: under the Scheme, not later than 7 days before the final date for payment, which falls 17 days after the due date. One day late and the notified sum is due in full. Set-off and contra charges need a valid pay less notice too. As of Oct 2026.
HGCRA 1996 ss.110A, 110B and 111; the Scheme for Construction Contracts
| Paid by the main contractor | £35,500 |
| Contra charge deducted with no valid pay less notice | £12,500 |
| Notified sum due in full | £48,000 |
No payment notice was served, and your application stated the sum and its basis as the subcontract allows, so £48,000 is the notified sum. Write at once demanding the £12,500 balance. If it is still unpaid after the final date, give notice of intention to suspend.
- Work out the dates.The due date, the payment notice deadline, the pay less deadline and the final date, from the contract or from the Scheme where it applies. A pay less notice served after the pay less deadline is ineffective, even by one day. Under the Scheme that deadline is 7 days before the final date, not the final date itself.
- Demand the full notified sum in writing.Cite section 111, and claim interest from the day after the final date at the contract rate, or under the Late Payment of Commercial Debts Act.
- Give notice before suspending.If the sum is still unpaid after the final date, serve a notice of intention to suspend stating the grounds, the final date that passed and the work affected. Wait at least 7 full days counted from the day after service: a notice served on day 0 allows suspension from day 8.
- Adjudicate.Adjudication is available at any time on a construction contract and runs to a 28-day timetable. It does not need the pre-action protocol. A construction solicitor or claims consultant should sign off the notice and referral.
Pay now, argue the true value later
A payer that missed its notice cannot hold the money while it runs its own true-value adjudication. It must pay the notified sum first, then adjudicate the true value.
Grove Developments v S&T [2018] EWCA Civ 2448
Interest adds up. On the unpaid £12,500 in the example, where the contract sets no rate of its own, interest at 11.75% a year is about £4.02 a day from the day after the final date, plus fixed compensation under the Late Payment of Commercial Debts Act. As of Oct 2026.
Without a valid notice the deduction is not allowed, however strong the contractor thinks its case is. It can argue the true value later, after paying.
Pay-when-paid, retention and insolvency
- A clause paying you only once the main contractor is paid is ineffective outside the insolvency exception. Use the Scheme timetable and claim interest.
- Retention held past its release date on finished work is a debt: send each job's statement and a demand with interest, and adjudicate if it is ignored.
- If the main contractor goes into administration, do not assume you can stop work. Check the subcontract, any moratorium and whether a suspension right has already arisen, and take insolvency advice first. Secure unfixed goods where your title clause works, prove the debt and reconcile CIS.
- Working past a letter of intent cap with no signed contract: stop at the cap until you have written authority, and take legal advice.
If the client is a homeowner
None of the Construction Act steps apply to a homeowner's work on their own home. Fix any genuine snags in writing, price the disputed items separately, then send a letter before claim under the Pre-Action Protocol for Debt Claims (the client gets 30 days to reply) and use the small claims track for claims up to £10,000 in England and Wales. If they threaten a bad review, reply factually and without their personal details. As of Oct 2026.
Work out the payment dates the day you send each application, not the day the money fails to arrive. By then the pay less deadline has already passed, and the first thing you need to know is whether it was met.
Asked in Greymill
With no payment notice, your application sets the notified sum if it stated the sum and its basis as the subcontract allows. Any deduction, contra charges included, needs a pay less notice stating the sum and the basis, served by the contract's deadline.
Under the Scheme (the default payment rules), that is no later than 7 days before the final date for payment (As of Oct 2026). One day late and it does not count.
Check that email's date and wording.
They can argue the true value later, but they pay first.
1. Today: demand the £12,500 in writing, citing section 111, with interest from the day after the final date.
2. Still unpaid after the final date: serve notice of intention to suspend, then wait at least 7 full days.
3. Or adjudicate: open at any time, on a 28-day timetable.
Have a construction solicitor or claims consultant check any suspension notice or referral.
Want the demand letter drafted?
Ask it about your own business
Paste this into Greymill with your own figures, and Contracts & Disputes works it through for your business.
I run a construction or building business in the UK. On [job], for [main contractor], I applied for [amount] on [date]. The contract is [JCT, NEC, bespoke, or none signed] and its payment terms are [paste them]. I received [a payment notice, a pay less notice, or nothing] on [date] and was paid [amount] on [date]. Work out the payment dates, tell me whether the deduction is valid, and draft the letter, the notice of intention to suspend or the adjudication steps I should take next.
More for construction and building in the UK
- Setting a day rate that still pays after holidays, rain days and the vanWork out what an hour of labour really costs you, then price for the margin you want, not a markup that looks like it.Read the lesson
- Busy on three jobs and still short for Friday's wagesWhy builders run out of cash while making a profit, and the weekly forecast, applications and retention ledger that close the gap.Read the lesson
- Quoting the wrong VAT rate on a building job and paying it out of my marginAs of Oct 2026, building work can be 0%, 5% or 20% VAT depending on what is being built, and the rate has to be settled before you quote.Read the lesson
- Starting a job before building control, party wall notices and the phase plan are sortedNo general licence is needed to trade as a builder in the UK, but building control, party walls, CDM and asbestos all have to be dealt with before the first day on site.Read the lesson
- Homeowner or main contractor: the paperwork that decides whether I get paidA homeowner job runs on consumer law and a job for a business runs on the Construction Act, so the paperwork you need and the clauses to strike are different.Read the lesson
- My regular labour-only subbie looks more like an employee every yearCIS registration does not make someone self-employed. How to tell, what it costs if HMRC disagrees, and the checks builders skip when they take people on.Read the lesson
- Proving to homeowners, main contractors and councils that I am a safe pair of handsEach kind of client checks different proof: reviews and trust marks for homeowners, accreditation for main contractors, registration for public tenders.Read the lesson
Open the interactive lesson · Every construction and building lesson · What Greymill knows about the trade
Sources
The primary sources behind this lesson, checked Oct 2026.
- s.111; Grove [2018] EWCA Civ 2448; s.112; Late Payment Act s.5A (Hard cases: payment, contracts and defects)
- ss.130, 135; Limitation Act s.4B (Hard cases: payment, contracts and defects)
- Small claims track (Hard cases: payment, contracts and defects)
- regs 19, 31, 36 (Hard cases: payment, contracts and defects)
- s.108(2)(a) (Hard cases: payment, contracts and defects)
- s.113 (Hard cases: payment, contracts and defects)
- regs 31 and 36(6) (Who must sign off: time-critical steps first)
- regs 4, 5 and Sch 1 (Who must sign off: time-critical steps first)
- ss.5, 8, 4B (Who must sign off: time-critical steps first)
- How to get approval (Who must sign off: time-critical steps first)
- Control of Asbestos Regulations 2012 reg 8 (Who must sign off: time-critical steps first)
- regs 10, 13, Sch 2 and 3 (Deliverables in house style)
- s.110A(1) (Deliverables in house style)
- s.112(2) (Deliverables in house style)
- paras 8.1, 8.5, 10.1 (Deliverables in house style)
- paras 3.1, 4 (Deliverables in house style)
- JCT 2024 Edition launch (Contract forms, RETENTIONS, insolvency and disputes)
- NEC4 ECC (Contract forms, RETENTIONS, insolvency and disputes)
- Cavendish Square Holding v Makdessi; ParkingEye v Beavis [2015] UKSC 67, para 32 (Contract forms, RETENTIONS, insolvency and disputes)
- Triple Point Technology v PTT [2021] UKSC 29 (Contract forms, RETENTIONS, insolvency and disputes)
- MT Hojgaard v E.ON [2017] UKSC 59 (Contract forms, RETENTIONS, insolvency and disputes)
- Monthly returns; paying (The calendar: CIS, payment notices, VAT, PAYE and self assessment)
- Deadlines (The calendar: CIS, payment notices, VAT, PAYE and self assessment)
- End of year (The calendar: CIS, payment notices, VAT, PAYE and self assessment)
- Deadlines (The calendar: CIS, payment notices, VAT, PAYE and self assessment)
- Chancellor letter of 31 July 2026 (The calendar: CIS, payment notices, VAT, PAYE and self assessment)
- CIS 340 sections 4.5 and 4.18 (The calendar: CIS, payment notices, VAT, PAYE and self assessment)
- regs 2 and 12; Sch 7 para 2 (Pitfalls that embarrass the product)
- s.106(1)(a) (Pitfalls that embarrass the product)
- s.61 (Pitfalls that embarrass the product)
- Commencement and the Central Digital Platform (Pitfalls that embarrass the product)
- Autoclenz v Belcher [2011] UKSC 41; Ready Mixed Concrete [1968] 2 QB 497 (Pitfalls that embarrass the product)
- [2018] EWCA Civ 2448 (Pitfalls that embarrass the product)
- s.108A (Contract red flags)
- s.8 (Contract red flags)